Peculiarities of application of british measurement systems in construction and their implementation on road facilities in Ukraine

published:
Number: Issue 29 (2024)
Section: Economy. Management
The page spacing of the article: 25-33
Keywords: CESMM, BoQ, bill of quantities, measurement, road construction, international measurement system, scope of work.
How to quote an article: Artem Bezuglyi, Volodymyr Kaskiv, Sergii Illiash, Yulia Makovska, Tetiana Stasiuk, Volodymyr Vasylenko. Peculiarities of application of british measurement systems in construction and their implementation on road facilities in Ukraine. Dorogi і mosti [Roads and bridges]. Kyiv, 2024. Issue 29. P. 25–33 [in Ukrainian].

Authors

State Enterprise «National Institute for Development Іnfrastructure» (SE «NIDI»), Kyiv, Ukraine
http://orcid.org/0000-0003-3883-7968
State Enterprise «National Institute for Development Infrastructure» (SE «NIDI»), Kyiv, Ukraine
https://orcid.org/0000-0002-3001-8012
State Enterprise «National Institute for Development Infrastructure» (SE «NIDI»), Kyiv, Ukraine
https://orcid.org/0000-0001-5921-4503
State Enterprise «National Institute for Development Іnfrastructure» (SE «NIDI»), Kyiv, Ukraine
https://orcid.org/0000-0002-8074-6798
State Enterprise “National Institute for Development Infrastructure“ (SE “NIDI”), Kyiv, Ukraine
https://orcid.org/0000-0003-1107-7727

Summary

Introduction. The article provides an overview of international measurement systems for works and services on the example of Great Britain, the peculiarities of their application, the main advantages and disadvantages. Using the example of the Standard Method of Measurement in Civil Engineering (CESMM), the article discusses how such systems can contribute to accurate measurements, time and resource savings in road construction. The experience of applying CESMM4 on road facilities in Ukraine is also considered.

Problem statement. In construction in general, the use of international measurement systems is crucial for optimizing processes and improving the quality of project implementation. According to the requirements of the modern construction sector, the ability to generate bill of quantities (BoQ) according to international standards defines a new stage in the planning and implementation of construction projects.

The use of international measurement systems allows not only to standardize the scope of work and services but also ensures objectivity in the preparation of tender proposals. Obtaining information on the scope of work without prices according to international standards guarantees equality and objectivity in the evaluation and selection of a contractor. This approach also helps to unify communication between all participants in the construction process, which, in turn, increases the level of mutual understanding and promotes the implementation of modern technologies and best practices. However, today there is no clarity on the detailed measurement and description of construction works, as even within one country there are a number of systems for measuring works and services.

Objective. To consider the importance and benefits of using international measurement systems in the construction industry, in particular in the context of road works.

Materials and Methods. The article is a review. The article uses a systematic approach, which is a set of general scientific methodological principles (requirements) based on the consideration of objects as systems.

Results. The article highlights useful recommendations for road construction professionals on the use of the CESMM system and international measurement standards to improve the efficiency and quality of work.

Conclusions. The use of international measurement systems promotes standardization and unification in the industry and facilitates mutual understanding between different project parties.

References

1.      Bezuhlyi A. O., Bibyk Yu. M., Hresko I. L., Boiko M. O. Osoblyvosti novoi systemy tsinoutvorennia v dorozhnii haluzi ta shliakhy yii udoskonalennia (Features of the new pricing system in the road industry and ways to improve it). Dorohy i mosty. Vypusk 18. Р. 8–18. [in Ukrainian].

2.      Pro zatverdzhennia Pravyl vyznachennia vartosti budivnytstva, rekonstruktsii, remontu ta utrymannia avtomobilnykh dorih zahalnoho korystuvannia: Nakaz Ministerstva infrastruktury
Ukrainy vid 05.02.2022 № 273 / Baza danykh zakonodavstvo Ukrainy // Verkhovna rada Ukrainy URL: https://zakon.rada.gov.ua/laws/show/z0527-22#Text  (Last accessed 20.03.2024) [in Ukrainian].

3.      CESMM4: Civil Engineering Standard Method of Measurement, Fourth edition URL: https://www.icevirtuallibrary.com/doi/book/10.1680/cesmm.57517 (Last accessed 20.03.2024). [in English].

4.      Pro zatverdzhennia Metodyky vyznachennia vartosti dorozhnikh robit ta posluh shchodo vyznachennia vartosti novoho budivnytstva, rekonstruktsii, remontiv ta ekspluatatsiinoho utrymannia avtomobilnykh dorih zahalnoho korystuvannia. Nakaz Ministerstva infrastruktury Ukrainy vid 07.10.2022 № 753 / Baza danykh zakonodavstvo Ukrainy // Verkhovna rada Ukrainy URL: https://zakon.rada.gov.ua/rada/ show/v0753733-22#Text (Last accessed 20.03.2024) [in Ukrainian].

5.      SMM7 – Standard method of measurement of building works. Seventh edition. (Last accessed 20.03.2024) [in English].

6.      NRM 1 – Order of Cost Estimating and Cost Planning for Capital Building Works: NRM 1. RICS Books. (Last accessed 20.03.2024). [in English].

7.      Chapter 6. New rules of measurement: NRM2. URL: https://books-library.net/files/books-library.online-07241334Wr3K1.pdf (Last accessed 20.03.2024) [in English].

8.      BIM-Based Bill of Quantities Generator following POMI and NRM2 Methods of Measurement. URL: https://www.researchgate.net/publication/342625082_BIM-Based_ Bill_of_Quantities_Generator_following_POMI_and_NRM2_Methods_of_Measurement (Last accessed 20.03.2024) [in English].

9.      CESMM4. Designing Buildings URL: https://www.designingbuildings.co.uk/wiki/ CESMM4 (Last accessed 20.03.2024). [in English].

10.   DSTU 8747:2017 Avtomobilni dorohy. Vydy ta pereliky robit z remontiv ta ekspluatatsiinoho utrymannia (Automobile roads. Types and lists of repair and maintenance works). Kyiv. 2017. 48 s. (Informatsiia ta dokumentatsiia) [in Ukrainian].

11.   SOU 42.1-37641918-035:2018 Avtomobilni dorohy. Resursni elementni koshtorysni normy na remontno-budivelni roboty (Automobile roads. Resource elemental estimate standards for repair and construction works). Kyiv. 2018. 36 s. (Informatsiia chy dokumentatsiia) [in Ukrainian].

12.   CESMM4 Standartnyi metod vymiriuvannia v tsyvilnomu budivnytstvi. Vydannia chetverte. Perehlianute (Standard method of measurement in civil engineering. The fourth edition) URL:https://www.icevirtuallibrary.com/doi/suppl/10.1680/cessmfr. 64409/suppl_file/CESMM4_Revised_4ed_9780727764409_Ukrainian.pdf (Last accessed 20.03.2024) [in Ukrainian].